1. ) CHONG KOK SIONG 2. ) TEE AI LING 3. ) HON KAH SHIN 4. ) CHOW LAI LAI 5. ) SAH THIAM LEONG 6. ) LOW HUEY SUAN v MAWAR AWAL (M) SDN BHD

wa-22ncvc-521-08-2024 High Court (Mahkamah Tinggi) 18 March 2025 • WA-22NCvC-521-08/2024 • 15 min read
26 cases cited (0 SG, 26 foreign)

Catchwords

[1] This is an application by the Plaintiffs for a summary judgement to be entered against the Defendant (Enclosure 6) pursuant to Order 14 of the Rules of Court 2012 (ROC). [2] The Plaintiffs are claiming for liquidated ascertained damages (LAD) for late delivery of vacant possession and completing common facilities of condominium by the Defendant. [3] The Defendant is a developer of a housing project known as “Mulberi Kondominium” (Project). [4] The well-established legal principles applicable to applications for summary judgment have been clearly and expressly deliberated as provided by statutory provisions and decided cases. [5] This Court finds that the matter in question is only about the calculation of the LAD and which calculation, whether the Plaintiffs or the Defendant, as correct? In this regard, this Court finds that the calculation of the Defendant has a basis and had given such order accordingly. [6] After careful scrutiny and judicious consideration of all the evidence before this Court, including the written and oral submissions of both parties, this Court in allowing Enclosure 6 has ordered the Defendant to pay as follows- “1. Gantirugi tetap yang berjumlah RM 556,560.00 dibayar oleh Defendan kepada Plaintif Pertama dan Plaintif Ke-2; 2. Gantirugi tetap yang berjumlah RM 580,411.28 dibayar oleh Defendan kepada Plaintif Ke-3 dan Plaintif Ke-4; 3. Gantirugi tetap yang berjumlah RM 487,851.16 dibayar oleh Defendan kepada Plaintif Ke-5 dan Plaintif Ke-6; 4. Faedah atas perenggan-perenggan 1-3 di atas pada kadar 5% setahun dari tarikh tuntutan ini iaitu pada 5-8-2024 sehingga pembayaran penuh dan muktamad dibayar oleh Defendan kepada Plaintif-Plaintif; dan kos...”.

Practice Areas

Judges (1)

Parties (7)

Case Significance

Illustrates summary judgment for statutory liquidated ascertained damages, where a Schedule H sale and purchase agreement establishes the developer's late-delivery liability and only the quantum of LAD remains to be determined.

This High Court decision at Kuala Lumpur concerns an application for summary judgment under Order 14 of the Rules of Court 2012 by a group of condominium purchasers against the developer of their project. The purchasers claimed liquidated ascertained damages (LAD) for the developer's late delivery of vacant possession and late completion of the common facilities of the condominium. Their purchases had been made under statutory sale and purchase agreements in the form prescribed by Schedule H to the Housing Development (Control and Licensing) Regulations 1989, which fixes both the developer's delivery obligations and the rate at which LAD accrues for delay.

Because the agreements were in the prescribed statutory form, the entitlement to LAD for late delivery followed from the contract itself, and the developer's liability in principle was not genuinely in dispute. The court applied the established summary-judgment principles: once the plaintiffs establish a claim to which there is no bona fide defence, the burden shifts to the defendant to show, on affidavit evidence amounting to more than bare denial, that there is a triable issue fit for trial. The court emphasised that denials in a defence are not themselves evidence; they are merely challenges to the other side to prove its case, and a defendant must put forward material on oath disclosing a defence.

Examining the affidavits, the court found that the only live question was the calculation of the LAD, namely which side's method of computing the damages was correct, rather than whether any LAD was owed at all. It held that this was a straightforward matter with no triable issue requiring a full trial, and it accepted that the developer's calculation had a proper basis. The court accordingly entered summary judgment in favour of the purchasers, awarding the LAD as computed together with interest at 5% per annum from the date of the claim until full payment, and costs. The judgment is a useful illustration of summary judgment for statutory LAD, where the developer's delay is established by the Schedule H agreement and only the quantum of damages remains to be fixed.

Why was the developer's liability suitable for summary judgment?

The purchases were made under sale and purchase agreements in the prescribed Schedule H form, which fixes the developer's delivery obligations and the LAD rate. Because the entitlement to LAD for late delivery followed from the statutory contract, liability was not genuinely in dispute, and the only live question was the calculation of the damages.

What did the court decide on the summary-judgment application?

The court held there was no triable issue requiring a trial, since the matter concerned only how the LAD should be calculated, and it accepted that the developer's calculation had a proper basis. It entered summary judgment for the purchasers, awarding the LAD with interest at 5% per annum from the date of the claim and costs.

Statutes Cited

Rules of Court 2012

Cases Cited (26)

MY (26)
[1975] 1 MLJ 85 [1981] 1 MLJ 282 [1983] 1 MLJ 206 [1984] 1 MLRH 509 [1984] 2 CLJ 220 [1984] 2 MLJ 300 [1986] 1 MLJ 240 [1987] 2 MLJ 332 [1992] 1 CLJ 627 [1992] 1 MLJ 400 [1995] 2 MLJ 363 [1998] 1 AMR 657 [2003] 3 CLJ 497 [2003] 4 MLJ 441 [2006] 2 MLJ 685 [2006] 3 CLJ 544 [2011] 2 MLJ 141 [2011] 9 CLJ 833 [2012] 1 MLJ 27 [2020] 1 MLJ 281 [2021] 2 CLJ 441 [2021] 2 MLJ 60 [2022] MLJU 2682 [2023] 6 CLJ 232 [2023] MLJU 2483 [2023] MLJU 891

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (wa-22ncvc-521-08-2024)