YAP WEI SHENG v SINERJUTA SDN. BHD

wa-12ancvc-154-08-2024 High Court (Mahkamah Tinggi) 10 April 2025 • WA-12ANCvC-154-08/2024 • 15 min read
3 cases cited (0 SG, 3 foreign)

Catchwords

Practice Areas

Judges (1)

Counsel (4)

Parties (2)

Case Significance

Reaffirms that striking out under Order 18 rule 19 of the Rules of Court 2012 is confined to plain and obvious cases, and should not be used to dispose of a sale-and-purchase dispute turning on the construction of an extension-of-time letter.

This High Court decision concerns the proper approach to striking out a claim under Order 18 rule 19(1)(a) to (d) of the Rules of Court 2012, in the context of a buyer's claim against a developer. The appellant had brought a writ and amended statement of claim in the Sessions Court alleging breach of a sale and purchase agreement, principally the late delivery of effective vacant possession and a claim for liquidated ascertained damages. The Sessions Court Judge struck out the claim on the developer's application. On appeal, the High Court held that the Sessions Court Judge had erred in allowing the striking-out application, allowed the appeal, and ordered the case remitted to the Sessions Court for trial before a different judge.

At the heart of the reasoning was the principle that the summary power to strike out is to be exercised sparingly and only in plain and obvious cases, not where the pleadings raise triable questions. The court identified genuinely contestable issues that could not be resolved without a trial. One turned on the effect of an extension-of-time arrangement recorded in a letter dated 1 September 2022, whose paragraph 7 provided in Malay: "Kegagalan mematuhi syarat-syarat yang dinyatakan di atas akan menyebabkan kelulusan ini terbatal dan pemaju dikehendaki menanggung bayaran pampasan kelewatan penyerahan hakmilikan kosong kepada pembeli" (failure to comply with the stated conditions will cause this approval to be void, and the developer must bear compensation for the late delivery of vacant possession to the purchaser). Whether the developer's non-compliance had voided the extension by its own terms, so as to revive the buyer's entitlement to liquidated ascertained damages, was a question fit for trial rather than summary determination.

The court also noted a further pleaded breach — an alleged failure to construct the parcel in accordance with the approved plan — which similarly required evidence. The judgment is a useful illustration of the reluctance of the appellate court to endorse the striking out of a sale-and-purchase dispute that turns on the construction and effect of an extension-of-time letter.

Why did the High Court set aside the striking-out order?

The High Court held that the Sessions Court Judge had erred, because the pleadings raised triable issues — including whether a developer's non-compliance had voided an extension of time and revived the buyer's claim for liquidated ascertained damages — that could not properly be resolved on a summary striking-out application.

What order did the High Court make?

It allowed the appeal and remitted the case to the Sessions Court for trial before another Sessions Court Judge.

Statutes Cited

Cases Cited (3)

MY (3)
[1993] 3 MLJ 36 [2016] 3 CLJ 1 [2021] 2 CLJ 441

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (wa-12ancvc-154-08-2024)