COVA DESIGN & CONTRACT SDN. BHD. v INTBUILD CONCEPT SDN. BHD.

ba-12bncc-4-03-2025 High Court (Mahkamah Tinggi) 14 August 2025 • BA-12BNCC-4-03/2025 • 17 min read
9 cases cited (0 SG, 9 foreign)

Outcome

Berdasarkan alasan-alasan di atas, rayuan defendan telah dibenarkan setakat yang berikut - (i) Keseluruhan keputusan Mahkamah Sesyen diketepikan termasuk kos; (ii) Pampasan gantirugi sebanyak RM360,000.00; (iii) RM86,890.66 bagi kos dan perbelanjaan membaiki kecacatan kerja-kerja setakat Mei 2021; (iv) Plaintif diperintahkan menarik balik dan membatalkan laporan yang dibuat daripada rekod CTOS dalam masa 7 hari dari tarikh perintah ini.

Quoted verbatim from the judgment of High Court (Mahkamah Tinggi) (ba-12bncc-4-03-2025). Read the full judgment on the official Malaysia Courts portal for the complete decision.

Catchwords

RAYUAN SIVIL: Tuntutan utama melibatkan Intrabuild Concept Sdn Bhd selaku plaintif dengan defendan, Cova Design & Contract Sdn Bhd untuk mendapatkan baki bayaran bagi kerja-kerja yang dijalankan oleh plaintif berjumlah RM84,255.52 berserta faedah dan kos. Defendan merupakan kontraktor utama bagi projek Cadangan Pemajuan 3 Blok Pangsapuri Perkhidmatan (1,843 unit) yang mengandungi 3 blok pangsapuri perkhidmatan terdiri daripada Blok A (587 unit), Blok B 28 tingkat (725 unit), Blok C 28 tingkat (531 unit), Blok 1 Tingkat Kemudahan dan 7 Tingkat Podium Tempat Letak Kereta dan 2 tingkat sub-basement berserta kemudahan berkaitan di atas Lot PTD 25671 (sebahagian Lot Asal 64369) Jalan Sagu 36, Taman Daya, Mukim Terbau, Daerah Johor Bahru, Johor untuk Tetuan Casa Andaman Sdn Bhd. Defendan melantik plaintif sebagai sub-kontraktor bagi kerja-kerja pemasangan perabot yang dinyatakan dalam Surat Pelantikan Pertama bertarikh 12.2.2019. Kerja-kerja telah diselesaikan oleh plaintif dan invois-invois dikeluarkan bagi menuntut fi kontrak berbaki RM335,638.80 yang merangkumi Tuntutan Progres No. 13 bagi RM222,339.75 bertarikh 18.4.2020, Tuntutan Progres Akhir RM35,564.25 bertarikh 15.6.2020 dan Tuntutan Akhir bagi pelepasan tahanan bertarikh 11.9.2020 berjumlah RM77,734.80. Bagi melunaskan invois-invois tersebut, defendan memberikan 6 cek tertunda kepada plaintif. Kesemua cek tersebut berjaya ditunaikan oleh plaintif kecuali cek kelima dan keenam berjumlah RM94,255.52 yang dikembalikan oleh pihak bank dengan catatan Payment Stopped/ Payment Countermanded (Technical). Defendan selanjutnya membayar RM10,000 kepada plaintif melalui cek No. 863646 bertarikh 28.5.2021 sebagai pembayaran sebahagian untuk cek kelima. Namun defendan gagal menjelaskan baki RM84,255.52 kepada plaintif sehingga menyebabkan plaintif memfailkan tuntutan di Mahkamah. Defendan memasukkan tuntutan balas yang antara lain memplidkan selain daripada fi kontrak yang dipersetujui dalam Surat Pelantikan Kedua, kerja-kerja hendaklah disiapkan oleh plaintif tertakluk kepada syarat bahawa pada atau sebelum 15.3.2020 bagi Tingkat 7 sehingga Tingkat 15 (152 unit); dan pada atau sebelum 5.2.2020 bagi Unit khas No. C-07-01, C-0709, C-07-15, C-08-19, C-09-06, C-09-12, C-10-15; C-12-15 dan C-14-07. UNDANG-UNDANG KONTRAK: Sama ada berlaku kelewatan oleh plaintif dalam menyiapkan Unit-unit Biasa dan sama ada defendan berhak menuntut LAD terhadap plaintif – Sama ada defendan berhak kepada tuntutan kos pembaikan kecacatan kerja-kerja plaintif – Sama ada defendan berhak terhadap gantirugi akibat dakwaan keberhutangan dalam rekod CTOS – s.74(1) dan s.75 Akta Kontrak 1950.

Practice Areas

Judges (1)

Counsel (6)

Parties (2)

Case Significance

Illustrates the assessment of liquidated ascertained damages and rectification costs under sections 74(1) and 75 of the Contracts Act 1950 in a construction subcontract, and recognises a remedy where a debt is wrongly maintained in a credit-reporting record after payment.

This High Court decision concerns a main contractor's appeal against the dismissal of its counterclaim in a subcontract dispute over the installation of built-in furniture in a large service-apartment development. The subcontractor had sued in the Sessions Court to recover a balance of RM84,255.52 for work done, the debt arising after two of six post-dated cheques issued by the main contractor were dishonoured with the notation that payment had been stopped. The main contractor counterclaimed, alleging that the subcontractor had delayed completion of the units against the deadlines fixed in a second letter of appointment, that its work was defective, and that it had suffered loss from an adverse credit record. The Sessions Court dismissed the counterclaim after a full trial and awarded costs against the main contractor, which appealed. The court examined whether the subcontractor had delayed in completing the units and whether the main contractor was entitled to liquidated ascertained damages, whether it could recover the cost of rectifying defective work, and whether it was entitled to damages for the continued reporting of the debt in a credit-reporting record, applying sections 74(1) and 75 of the Contracts Act 1950. Allowing the appeal in part, the court set aside the Sessions Court's decision, including costs, and awarded the main contractor liquidated damages of RM360,000.00 and RM86,890.66 for the cost of rectifying defects up to May 2021. It ordered the subcontractor to withdraw and cancel the credit report within seven days, and awarded nominal damages of RM2,000.00 for the continued reporting of the debt after the judgment sum had been settled, together with interest at 5% and costs of RM15,000.00. The judgment is a useful illustration of how the courts assess entitlement to liquidated ascertained damages and rectification costs under the Contracts Act 1950 in a construction subcontract, and of the availability of a remedy where a debt is wrongly maintained in a credit-reporting record after payment.

What did the High Court award the main contractor on its counterclaim?

Allowing the appeal in part, the court awarded liquidated ascertained damages of RM360,000.00 and RM86,890.66 for the cost of rectifying defective work up to May 2021, applying sections 74(1) and 75 of the Contracts Act 1950, together with interest and costs, and set aside the Sessions Court's dismissal of the counterclaim.

What remedy was given for the credit-record complaint?

The court ordered the subcontractor to withdraw and cancel the adverse credit report within seven days and awarded nominal damages of RM2,000.00 for the continued reporting of the debt in the credit-reporting record after the judgment sum had been settled.

Statutes Cited

Cases Cited (9)

UK (1)
[1947] AC 484
MY (8)
[2003] 4 MLJ 357 [2004] 4 CLJ 309 [2005] 2 MLJ 1 [2010] 9 CLJ 785 [2014] 2 CLJ 773 [2015] 2 MLJ 441 [2019] 1 MLJ 281 [2019] 6 MLJ 15

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (ba-12bncc-4-03-2025)