MRCB Sentral Properties Sdn Bhd v GSIB Sdn Bhd

wa-24carb-44-10-2025 High Court (Mahkamah Tinggi) 29 January 2026 • WA-24C(ARB)-44-10/2025 • 3 min read

Catchwords

Practice Areas

Judges (1)

Parties (2)

Case Significance

Illustrates the enforcement side of arbitral finality under the Arbitration Act 2005: where an award-debtor's resistance amounts only to a merits disagreement about delay, extension of time and LAD, no section 37 ground is made out and the court recognises and enforces the award under section 38.

This High Court decision is the companion enforcement proceeding to the challenge against a Final Award made in a construction arbitration, here framed as the application by MRCB Sentral Properties Sdn Bhd to recognise and enforce the Award against GSIB Sdn Bhd. Heard together with the setting-aside application, the two originating summonses under the Arbitration Act 2005 raised, from opposite directions, the single question whether the Award should stand.

The court approached enforcement through the same statutory lens that governs a challenge. The award-debtor's resistance rested on section 37(1)(b)(ii) of the Arbitration Act 2005 — that the Award should be set aside for a breach of natural justice and conflict with public policy — with the substance of the objection lying in the arbitrator's findings on delay analysis, extension of time and liquidated ascertained damages (LAD). The court held that those were "decisions on the merits" of the construction dispute, and that dissatisfaction with them does not establish a breach of natural justice or a conflict with public policy. The supervisory role of the court under the Act is not to re-open the merits of the arbitrator's evaluation.

Because the Award disclosed "no material breach of natural justice", the court dismissed the setting-aside application and, in this proceeding, allowed recognition and enforcement of the Award under section 38 of the Act. The result reflects the pro-enforcement policy of the Arbitration Act 2005: an award that is not shown to fall within a section 37 ground is to be recognised and enforced as of course.

The judgment is a useful illustration of the enforcement side of arbitral finality in Malaysia. Where an award-debtor's only complaint is a merits disagreement about delay, extension of time and LAD, the court will not withhold enforcement under section 38; the finality of the arbitral process is preserved and the successful party obtains the fruits of its award.

What was sought in this proceeding?

Recognition and enforcement of the Final Award under section 38 of the Arbitration Act 2005, in favour of the award-creditor, against the award-debtor's resistance based on the same section 37(1)(b)(ii) grounds raised in the companion setting-aside application.

Why was enforcement allowed?

Because the arbitrator's findings on delay, extension of time and LAD were decisions on the merits disclosing no material breach of natural justice or conflict with public policy; with no section 37 ground established, the court dismissed the setting-aside application and enforced the Award under section 38.

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (wa-24carb-44-10-2025)