GRAND DYNAMIC BUILDERS SDN. BHD. v DAMAI CITY SDN. BHD.

wa-24c-143-09-2024 High Court (Mahkamah Tinggi) 20 April 2025 • WA-24C-143-09/2024 • 34 min read
14 cases cited (0 SG, 14 foreign)

Outcome

I therefore dismiss the application under enclosure1 with costs. Decision [69] To surmise, I do not find any merits in the contentions raised by DCSB in the matter before me and to quote the UK Court of Appeal in Carillion Construction Ltd v Davenport Royal Dockyard Ltd [2005] EWHC 778 this is, with respect, a case of DCSB “…simply scrabbling around to find some argument however tenous, to resist payment”. [70] I therefore dismiss both Enclosure 1 and Enclosure 11 in Originating Summons No.

Quoted verbatim from the judgment of High Court (Mahkamah Tinggi) (wa-24c-143-09-2024). Read the full judgment on the official Malaysia Courts portal for the complete decision.

Catchwords

Practice Areas

Judges (1)

Counsel (7)

Parties (2)

Case Significance

The companion CIPAA ruling confirming, from the contractor's side, the enforceability of an adjudication decision and the confined grounds for setting aside under sections 15(b) and (d) and for a stay under section 16(1)(b), the paying party's challenge being dismissed with costs.

This High Court (Kuala Lumpur) decision is the companion originating summons, heard together with the related matter, concerning an adjudication decision made under the Construction Industry Payment and Adjudication Act 2012 (CIPAA) in favour of the contractor, Grand Dynamic Builders Sdn Bhd, against Damai City Sdn Bhd. The adjudication decision dated 20 August 2024, issued by the appointed adjudicator, was the subject of parallel applications: an application by the employer to set it aside under sections 15(b) and (d) of CIPAA and to stay it under section 16(1)(b), and this related summons brought under Order 7, Order 28 and Order 69A of the Rules of Court 2012, in which the contractor's position as adjudication claimant was in issue.

The court considered the applications against the statutory purpose of CIPAA, namely to provide a rapid adjudication mechanism that secures cash flow for a contractor who has carried out its work and is out of pocket. It reiterated that the grounds for setting aside under sections 15(b) and (d) are confined, addressing excess of jurisdiction and breach of natural justice, and that a stay under section 16(1)(b) does not follow automatically from the making of an application.

Dismissing the challenge, the court held that treating a section 16(1)(b) application as automatically staying the adjudication decision would be tantamount to a backdoor mechanism to denude and deplete the decision of its efficacy, stultifying and stymieing the purpose of CIPAA. It found no merit in the contentions raised against the adjudication decision, quoting the English Court of Appeal in Carillion Construction Ltd v Davenport Royal Dockyard Ltd to the effect that the resisting party was, with respect, scrabbling around to find some tenuous argument to resist payment. The applications were dismissed with costs. From the contractor's standpoint, the judgment confirms the enforceability of the adjudication decision and the limited scope for a paying party to set aside or stay it under CIPAA.

How does this summons relate to the companion matter?

It is the related originating summons heard together concerning the same adjudication decision of 20 August 2024 in favour of Grand Dynamic Builders Sdn Bhd, in which the employer's setting-aside and stay applications were resisted.

What did the court decide?

It dismissed the challenge with costs, holding the setting-aside grounds under sections 15(b) and (d) of CIPAA were not made out and a section 16(1)(b) stay is not automatic, so the adjudication decision remained enforceable in line with CIPAA's cash-flow purpose.

Statutes Cited

Rules of Court 2012

Cases Cited (14)

UK (5)
[1940] 1 All ER 425 [1940] AC 412 [1950] 2 All ER 549 [1951] Ch 112 [2005] EWHC 778
MY (9)
[2010] MLJU 103 [2011] 1 MLJ 752 [2018] 2 MLJ 22 [2018] MLJU 1711 [2019] 2 MLJ 689 [2019] MLJU 1215 [2019] MLJU 162 [2024] 2 MLJ 543 [2024] 4 MLJ 405

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (wa-24c-143-09-2024)