JM Letrik Sdn. Bhd. v Gas Malaysia Distribution Sdn Bhd

ja-12bncvc-18-08-2024 High Court (Mahkamah Tinggi) 28 August 2025 • JA-12BNCvC-18-08/2024 • 21 min read
5 cases cited (0 SG, 5 foreign)

Catchwords

TORT: Kecuaian — Kerja pemasangan kabel kuasa melalui HDD — Paip gas rosak dan kebocoran gas — Kewajipan berjaga-jaga diakui saksi — Pelanggaran kewajipan: tidak mematuhi lukisan profil diluluskan; gagal mengekalkan jarak sekurang-kurangnya tiga meter; gagal mendedahkan semula paip apabila jarak kurang daripada tiga meter; kerja tanpa permit dan tanpa pengawasan Plaintif; subkontraktor tidak kompeten — Kaitan sebab-akibat dan kebolehramalan dibuktikan — Elemen kecuaian dipenuhi atas imbangan kebarangkalian. UTILITI / KESELAMATAN GAS: Permit kerja harian dan keperluan pengawasan pemegang utiliti — Kegagalan memohon permit bagi 1 dan 2 Oktober 2020 — Pelanggaran syarat keselamatan kerja berhampiran paip gas bertekanan. KETERANGAN: Kuantum kerugian dibuktikan melalui SP3 dan dokumen sokongan — Kos pembaikan, bahan, tenaga kerja, kenderaan dan kehilangan gas — Jumlah keseluruhan RM744,271.24 — Tiada sanggahan substantif oleh Defendan — Pengakuan tanggungjawab oleh Pengurus Projek Defendan. PROSEDUR SIVIL: Beban pembuktian di bawah seksyen 101 dan 102 Akta Keterangan 1950 — Beban berpindah kepada Defendan setelah elemen dibuktikan — Defendan gagal menepis — Tuntutan terhadap pihak ketiga ditolak. RAYUAN: Prinsip “plainly wrong test” — Tiada salah arah undang-undang atau kekhilafan fakta — Dapatan fakta Mahkamah Sesyen dikekalkan — Lim Peng Hock & Anor v Chuah Peng San & Anor [2021] CLJU 119; Lee Ing Chin @ Lee Teck Seng v Gan Yook Chin & Anor [2003] 2 CLJ 19; Goh Bak Ming v Yeoh Eng Kong & Ors [2019] 1 CLJ 461 diikuti.

Practice Areas

Judges (1)

Counsel (4)

Parties (2)

Case Significance

Applies the 'plainly wrong' standard of appellate review to affirm a negligence finding against a contractor that damaged a pressurised gas pipe, illustrating the duty of care and permit and clearance requirements when working near utility infrastructure.

This High Court decision at Johor Bahru is an appeal from the Sessions Court in a negligence claim brought by a gas distribution company against an electrical and installation contractor. The contractor, engaged in laying power cable by horizontal directional drilling, had damaged a pressurised gas pipe and caused a gas leak. The Sessions Court had found the contractor negligent and ordered it to pay the gas company RM744,271.24 in damages, with interest at 5 percent per annum and costs of RM20,000, while dismissing the contractor's claim against a third-party insurer. On appeal, the contractor challenged both liability and quantum. The High Court reviewed the trial findings against the 'plainly wrong' standard of appellate review, under which a trial court's findings of fact will not be disturbed unless there was a misdirection in law or a demonstrable error. On the evidence, the breaches were clear: the contractor had not followed the approved profile drawing, had failed to maintain the required minimum clearance of three metres from the gas pipe, had failed to re-expose the pipe where the clearance fell short, and had worked without the necessary permit and without the utility owner's supervision, using a subcontractor found not to be competent. Causation and foreseeability were established, and the elements of negligence were made out on the balance of probabilities. On quantum, the amount had been proved through the plaintiff's witness and supporting documents covering repair, materials, labour, vehicles and lost gas, and had not been substantively challenged. The court further noted that the defendant's own project manager had acknowledged responsibility, and that the defendant had at no stage offered any explanation disputing the components of the loss claimed. Finding no basis to interfere, the High Court dismissed the appeal, affirmed the Sessions Court's decision, and ordered costs of RM5,000. The judgment illustrates the application of appellate restraint and the standard of care expected when working near pressurised utility infrastructure.

What negligence was established against the contractor?

The contractor had not followed the approved profile drawing, had failed to maintain the required three-metre clearance from the gas pipe, had failed to re-expose the pipe where clearance was insufficient, and had worked without a permit or the utility owner's supervision using an incompetent subcontractor — damaging a pressurised gas pipe and causing a leak.

What was the outcome of the appeal?

The High Court dismissed the appeal and affirmed the Sessions Court's decision, which had ordered the contractor to pay RM744,271.24 in damages with interest and costs, and had dismissed the contractor's third-party claim. Costs of RM5,000 were ordered on the appeal.

Cases Cited (5)

MY (5)
[2003] 2 CLJ 19 [2017] 5 MLJ 398 [2019] 1 CLJ 461 [2019] MLJU 594 [2020] MLJU 5861

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (ja-12bncvc-18-08-2024)