PERRESIA RESOURCES (M) SDN BHD v PERSPEKTIF MASA SDN BHD

bl-22ncvc-22-06-2023 High Court (Mahkamah Tinggi) 23 January 2025 • BL-22NCvC-22-06/2023 • 16 min read
2 cases cited (0 SG, 2 foreign)

Outcome

Therefore, for Suit 21 and Suit 22, both the Plaintiff’s claim is hereby dismissed with cost. The Plaintiff is to pay the Defendant in each suit RM 25,000.00 as cost.

Quoted verbatim from the judgment of High Court (Mahkamah Tinggi) (bl-22ncvc-22-06-2023). Read the full judgment on the official Malaysia Courts portal for the complete decision.

Catchwords

Practice Areas

Judges (1)

Parties (2)

Case Significance

Demonstrates that LAD and unjust-enrichment claims for late delivery cannot survive where a later Deed of Settlement supersedes the sale agreements and omits the remedy sought, and where the claimant has delayed unconscionably before enforcing its asserted rights.

This High Court decision at Klang is the second of two companion suits concerns companion suits, heard and decided together, over a claim for liquidated ascertained damages (LAD) for the late delivery of vacant possession of two condominium units. The plaintiff was the purchaser of two units in a development in Ampang built by the defendant developer, under two Sale and Purchase Agreements both dated 22 February 2011. The purchase price was said to have been satisfied by third-party consideration — a debt the defendant owed to a quantity-surveying firm — reflected in a Deed of Settlement dated 29 August 2013 between that firm and the defendant. Under the SPAs vacant possession was to be delivered within 36 months, by 21 February 2014, and the plaintiff claimed LAD for the delay.

The decisive issue was the standing and contractual basis on which the LAD could be claimed. The court addressed questions of locus standi and of who was the rightful owner or merely a nominee, noting the principle that an agent cannot sue or be sued on contracts entered into on behalf of a principal. It then found that the two SPAs had been superseded by the Deed of Settlement, and that the Deed contained no provision preserving any entitlement to LAD. With the sale agreements displaced by a later settlement silent on LAD, there was no contractual right on which the claim could rest. The court additionally held the claim to be defeated by laches and by inordinate and inexcusable delay, the plaintiff having acquiesced in the position for well over a decade.

The court dismissed the plaintiff's claim and ordered the plaintiff to pay the defendant costs of RM25,000 in this suit. Taken together with its companion, the decision demonstrates that unjust-enrichment and LAD arguments cannot survive where a subsequent settlement deed governs the transaction and omits the remedy sought, and where the claimant has delayed unconscionably before enforcing whatever rights it asserts.

What contractual issue defeated the claim?

The court found the two Sale and Purchase Agreements had been superseded by the 2013 Deed of Settlement, which contained no provision preserving any entitlement to LAD, leaving no contractual right on which the late-delivery claim could rest.

What did the court say about standing?

The court considered questions of locus standi and whether the claimant was the rightful owner or a nominee, noting that an agent cannot sue or be sued on contracts entered into on behalf of a principal.

What was the result?

The court dismissed the claim and ordered the plaintiff to pay the defendant costs of RM25,000 in this suit, also finding the claim barred by laches and inordinate delay.

Statutes Cited

Cases Cited (2)

MY (2)
[1986] 2 MLJ 30 [2024] MLJU 2205

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (bl-22ncvc-22-06-2023)