SILVERLAND CAPITAL SDN BHD v WEGROW GLOBAL SDN BHD

ba-22ncvc-207-05-2025 High Court (Mahkamah Tinggi) 1 October 2025 • BA-22NCvC-207-05/2025 • 8 min read
3 cases cited (0 SG, 3 foreign)

Catchwords

Practice Areas

Judges (1)

Counsel (4)

Parties (2)

Case Significance

Instructive on the threshold for attachment before judgment under section 19(1)(c) of the Debtors Act 1957, showing that large arrears, denial of liability and asset removal on exit can justify preventive interim security pending trial.

This High Court decision at Shah Alam concerns an application for attachment before judgment under section 19(1)(c) of the Debtors Act 1957. The plaintiff, Silverland Capital Sdn Bhd, the operator of an outlet mall in Perak, sought the order against the defendant, WeGrow Global Sdn Bhd, a commercial occupier operating a dinosaur-themed attraction at the mall. The plaintiff's case was that the defendant was in substantial arrears of rent and service charges exceeding RM2.29 million, had repudiated the binding effect of a tenancy arrangement recorded in a Heads of Terms dated 23 November 2023, and had taken steps to remove its property from the demised premises with intent to defeat execution of any judgment. Under the Heads of Terms the plaintiff had granted early possession of some 24,388 square feet of retail space, with rent computed at 20% of monthly gross ticket sales, or a fixed rate per square foot if the defendant failed to install an agreed point-of-sale system; the defendant paid a booking fee, carried out extensive renovations and began operations, but failed to install the point-of-sale system, defaulted on payments and disputed the binding effect of the Heads of Terms, its solicitors indicating an intention to vacate. The defendant resisted the application, contending that the Heads of Terms was not binding, that there was no good cause of action, and that there was neither intent to obstruct nor any act of removal or concealment of property. The court, per Dato' Anita binti Harun JC, held that the Heads of Terms was a concluded agreement acted upon by both parties and that the plaintiff's claim was genuine and legally sustainable, and found that the combination of large arrears, a complete denial of liability and steps to vacate while removing valuable assets justified an inference of intent to frustrate recovery. Emphasising that attachment before judgment is preventive, operating only as interim security while the plaintiff must still prove its claim at trial, the court allowed the application, restraining removal of the defendant's assets and the plaintiff's fixtures and attaching the defendant's movable property, with costs in the cause. The judgment is instructive on the threshold for attachment before judgment under the Debtors Act 1957.

What did the court order on the attachment application?

The court allowed the application under section 19(1)(c) of the Debtors Act 1957, restraining the defendant from removing its movable assets or interfering with the plaintiff's fixtures at the premises and attaching the defendant's movable property before judgment as interim security, with costs in the cause.

What justified the inference that the defendant intended to defeat execution?

The court found that the combination of arrears exceeding RM2.29 million, a complete denial of contractual liability under a concluded Heads of Terms, and steps to vacate the premises while removing valuable assets went beyond a routine exit and justified an inference of intent to frustrate recovery, warranting attachment before judgment.

Statutes Cited

Debtors Act
s 19
Debtors Act 1957
s 19(1)(c)

Cases Cited (3)

MY (3)
[1962] 1 MLJ 375 [1982] 1 MLJ 258 [2018] 5 MLJ 380

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (ba-22ncvc-207-05-2025)