TENAGA NASIONAL BERHAD v BATU KEMAS INDUSTRI SDN BHD
Outcome
Conclusion [60] As a result of the above findings, this Court hereby makes the following orders: (i) Appeal 242 – Government of Malaysia’s appeal is hereby dismissed; (ii) Appeal 243 – Batu Kemas’s appeal is hereby allowed to the effect that interest of 5% per annum is chargeable on the judgment debt to be calculated from the date of the judgment (17.3.2022) until to the date of full payment; (iii) Appeal 247 – TNB’s appeal is hereby allowed in part to the effect that paras (c), (d) and (e) of the High Court Order dated 17.3.
Catchwords
Practice Areas
Judges (3)
Counsel (12)
Case Significance
Illustrates appellate supervision of a damages assessment carried out under a Federal Court direction, the Court of Appeal adjusting particular heads of loss, interest and nominal damages across three consolidated appeals while holding that the High Court acted within the scope of that direction.
This Court of Appeal decision disposes of three consolidated appeals arising from the assessment of damages in a long-running dispute in the High Court at Ipoh, following an earlier Federal Court order that had settled liability and directed how damages were to be assessed. The plaintiff, an industrial company, had recovered against the Government of Malaysia and the national electricity utility, and the High Court had assessed the damages flowing from physical damage and consequential economic loss. The three appeals — one by the Government of Malaysia, one by the plaintiff company, and one by the utility — challenged different aspects of that assessment, raising issues about the quantum of loss and damage, including loss of goods in production and profits, loss of production and profits, the replacement cost of machinery and other equipment physically damaged and the cost of repairs, the discretion to award pre-judgment interest from the date of the incident or the date of filing, and the propriety of awarding damages on documents that had only been marked for identification. The Court examined whether the High Court had acted within the scope of the Federal Court order and direction, and held that it had, noting in particular that the Federal Court had treated replacement costs as part of the claim for economic loss consequent on physical damage. In the electricity utility's appeal, the Court allowed the appeal in part, to the effect that three specified paragraphs of the High Court order were to be amended so that the sums awarded under them became RM1,000 each as nominal damages. The Court ordered that a paragraph of the High Court order be deleted because the damages awarded in it had been subsumed in another head, that the judgment sum be amended to reflect its orders, and that the parties bear their own costs in all three appeals. The decision illustrates how an appellate court supervises an assessment of damages carried out under a superior court's direction, correcting particular heads while respecting the framework fixed by that direction.
Summary
TNB appealed against the High Court's assessment of damages in a long-running dispute with Batu Kemas Industri Sdn Bhd over factory losses from a 1998 incident, heard together with appeals by the Government and Batu Kemas. The Court of Appeal partially allowed TNB's appeal, reducing certain heads of damages for loss of goods, loss of production, and loss of profits to nominal damages of RM1,000 each, but upheld the RM35 million replacement cost for machinery. The parties were ordered to bear their own costs in all three appeals.
What was the outcome of the utility's appeal?
The Court allowed the utility's appeal in part, to the effect that three specified paragraphs of the High Court order dated 17 March 2022 were to be amended so that the sums awarded under them became RM1,000 each as nominal damages. The Court also ordered that a further paragraph be deleted because its damages had been subsumed in another head, and that the judgment sum be amended accordingly.
How were costs dealt with across the three appeals?
The Court ordered that the parties bear their own costs in all three appeals. Having dismissed the Government of Malaysia's appeal, allowed the plaintiff company's appeal on interest, and allowed the utility's appeal in part on certain heads of damages, it made no order shifting costs between the parties, leaving each to bear its own costs of the consolidated appeals.
Cases Cited (7)
Judgment
Read the full judgment on the official Malaysia Courts portal.
Read on eJudgmentSource: eJudgment (a-01w-247-04-2022)