Kerajaan Malaysia v BATU KEMAS INDUSTRI SDN BHD
Outcome
Conclusion [60] As a result of the above findings, this Court hereby makes the following orders: (i) Appeal 242 – Government of Malaysia’s appeal is hereby dismissed; (ii) Appeal 243 – Batu Kemas’s appeal is hereby allowed to the effect that interest of 5% per annum is chargeable on the judgment debt to be calculated from the date of the judgment (17.3.2022) until to the date of full payment; (iii) Appeal 247 – TNB’s appeal is hereby allowed in part to the effect that paras (c), (d) and (e) of the High Court Order dated 17.3.
Catchwords
Practice Areas
Judges (3)
Counsel (12)
Case Significance
Illustrates appellate supervision of a damages assessment carried out under a Federal Court direction, the Court of Appeal adjusting particular heads of loss, interest and nominal damages across three consolidated appeals while holding that the High Court acted within the scope of that direction.
This Court of Appeal decision disposes of three consolidated appeals arising from the assessment of damages in a long-running dispute in the High Court at Ipoh, following an earlier Federal Court order that had settled liability and directed how damages were to be assessed. The plaintiff, an industrial company, had recovered against the Government of Malaysia and the national electricity utility, and the High Court had assessed the damages flowing from physical damage and consequential economic loss. The three appeals — one by the Government of Malaysia, one by the plaintiff company, and one by the utility — challenged different aspects of that assessment, raising issues about the quantum of loss and damage, including loss of goods in production and profits, loss of production and profits, the replacement cost of machinery and other equipment physically damaged and the cost of repairs, the discretion to award pre-judgment interest from the date of the incident or the date of filing, and the propriety of awarding damages on documents that had only been marked for identification. The Court examined whether the High Court had acted within the scope of the Federal Court order and direction, and held that it had, noting in particular that the Federal Court had treated replacement costs as part of the claim for economic loss consequent on physical damage. In the first of the appeals, brought by the Government of Malaysia against the assessment, the Court found no basis to disturb the High Court's approach and dismissed that appeal. The Court ordered that a paragraph of the High Court order be deleted because the damages awarded in it had been subsumed in another head, that the judgment sum be amended to reflect its orders, and that the parties bear their own costs in all three appeals. The decision illustrates how an appellate court supervises an assessment of damages carried out under a superior court's direction, correcting particular heads while respecting the framework fixed by that direction.
Summary
The Government of Malaysia appealed against the High Court's assessment of RM35 million in replacement costs for machinery damaged in a 1998 incident involving Batu Kemas Industri Sdn Bhd's factory, following the Federal Court's order to reassess damages. The Court of Appeal dismissed the Government's appeal, upheld the RM35 million replacement cost award, allowed Batu Kemas's cross-appeal for 5% pre-judgment interest from the date of the High Court judgment, and partially allowed TNB's appeal by reducing certain heads of claim to nominal damages of RM1,000 each.
What did the Court of Appeal decide on the Government of Malaysia's appeal against the assessment?
The Court dismissed the Government of Malaysia's appeal. It held that the High Court judge had acted within the scope of the Federal Court order and direction in assessing the damages, including in treating replacement costs as part of the claim for economic loss consequent on physical damage, and found no basis to disturb the assessment on the grounds the Government advanced.
How did the Court treat the High Court's compliance with the Federal Court's direction?
The Court examined whether the High Court had acted within the scope of the Federal Court order and held that it had. It noted that the Federal Court had specifically directed that the assessment was to include the replacement cost of machinery or other equipment physically damaged, or the cost of repairs, so the High Court's award of such costs was consistent with the direction under which the assessment was carried out.
Cases Cited (7)
Judgment
Read the full judgment on the official Malaysia Courts portal.
Read on eJudgmentSource: eJudgment (a-01w-242-04-2022)