GLOMAC KRISTAL SDN BHD v NORTON CONSTRUCTION SDN BHD

wa-24carb-30-07-2025 High Court (Mahkamah Tinggi) 23 November 2025 • WA-24C(ARB)-30-07/2025 • 69 min read
24 cases cited (2 SG, 22 foreign)

Catchwords

Practice Areas

Judges (1)

Counsel (5)

Parties (2)

Case Significance

A developer's section 37 application to set aside a construction arbitration award dismissed because its natural-justice complaints were in truth a challenge to the arbitrator's merits and contractual interpretation.

This High Court decision concerns an application by a developer to set aside a construction arbitration award under section 37 of the Arbitration Act 2005, the developer having been the respondent in an arbitration commenced by a contractor over a building project. Section 37 confines the grounds on which a court may set aside an award to a closed list that includes a breach of the rules of natural justice in the making of the award; it is not a gateway to a rehearing of the merits.

The developer's principal complaint was that the arbitrator had breached natural justice by failing to consider material submissions, and that the arbitrator had wrongly preferred, or failed properly to weigh, expert-witness evidence that conflicted with the contemporaneous documentary record. The Court examined whether these complaints truly went to procedural fairness or whether, in substance, they were a challenge to the arbitrator's findings of fact and interpretation of the contract dressed up as natural-justice grounds. It held that they were the latter: the objections amounted to disagreement with the merits and with the arbitrator's contractual interpretation, matters that lie within the tribunal's province and are not reviewable under section 37. The governing principles of minimal curial intervention and the finality of arbitral awards meant the Court would not substitute its own view for the arbitrator's on how the evidence should have been assessed. Considerations of public policy did not assist the developer where no true procedural unfairness was shown.

The Court dismissed the setting-aside application with costs of RM20,000 subject to allocatur. The judgment is a useful illustration of the narrow scope of section 37, of the courts' insistence on minimal curial intervention and the finality of awards, and of how complaints that are in truth a challenge to an arbitrator's factual findings and contractual construction will not be entertained under the guise of a breach of natural justice.

Summary

Glomac Kristal sought to set aside a PAM arbitration final award under section 37 of the Arbitration Act 2005, alleging breach of natural justice and failure by the arbitrator to consider material submissions, while Norton Construction cross-applied to enforce the award under section 38. The court held that Glomac Kristal's complaints amounted to challenges on the merits and contractual interpretation rather than grounds for setting aside, and that the high threshold for curial intervention was not met. The setting aside application was dismissed with costs and the award was registered as a judgment of the High Court.

On what basis did the developer seek to set aside the award?

The developer applied under section 37 of the Arbitration Act 2005, alleging a breach of natural justice in that the arbitrator failed to consider material submissions and mishandled expert evidence that conflicted with the contemporaneous record.

Why did the setting-aside application fail?

The Court found the complaints were in substance a challenge to the arbitrator's factual findings and contractual interpretation rather than genuine procedural unfairness; applying minimal curial intervention and the finality of awards, it dismissed the application with costs of RM20,000.

Statutes Cited

GST Act 2014
s 9(3)
Rules of Court 2012

Cases Cited (24)

SG (1)
[2015] SGCA 18
SLR (1)
[2015] 3 SLR 488
MY (22)
[1989] 3 MLJ 2169 [2003] 4 MLJ 357 [2007] 4 MLJ 113 [2009] 2 MLJ 546 [2011] 6 MLJ 441 [2012] 8 MLJ 573 [2013] 2 CLJ 395 [2015] 1 MLJ 171 [2015] 2 MLJ 441 [2018] 7 MLJ 530 [2019] 2 MLJ 413 [2019] 3 MLJ 395 [2019] 6 CLJ 588 [2020] 12 MLJ 198 [2020] 3 MLJ 1 [2020] MLJU 399 [2021] 1 MLJ 1 [2022] MLJU 2286 [2022] MLJU 824 [2023] 12 MLJ 393 [2023] 6 MLJ 345 [2023] MLJU 3028

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (wa-24carb-30-07-2025)