KAYANGAN KEMAS SDN. BHD. v PEMBINAAN KERY SDN. BHD.

wa-22ncvc-452-07-2025 High Court (Mahkamah Tinggi) 9 December 2025 • WA-22NCvC-452-07/2025 • 6 min read
14 cases cited (0 SG, 14 foreign)

Catchwords

Assessment of Arguments of Parties [14] The Defendant raised various purported issues regarding the Plaintiff’s works. However, this was not raised at all after the issuance of the Certificate of Practical Completion or when negotiations for the settlement of outstanding amount were discussed whether between the parties or through their respective solicitors. [15] Moreover, the Defendant’s conduct in actively having participated in the settlement terms of payment, superseded any contended dissatisfaction. The Defendant is bound by the Settlement Agreement and must make good its contractual obligations. [16] The fact that there was the Settlement Agreement and that the Defendant was bound by it were not disputed by the Defendant. [17] This Court found the Defendant’s arguments that summary judgment ought not be granted as there were pending negotiations or rather that the negotiations were still on-going untenable. This Court found that the Settlement Agreement was concluded by both sides. Particularly so when the Defendant’s own conduct - in having paid not one but four instalments show without a doubt that the negotiations and agreement had been concluded. [18] This Court sighted the relevant multiple express agreement of the Defendant with regards the payment for the outstanding sum owed to the Plaintiff. The Defendant is estopped from raising issues on so-called defects when it did not feature at all during talks of settlement. This was most definitely a case where summary judgment is most appropriate. [19] There are no triable issues in the matter. [20] The following authorities were considered by this Court in determining this application: • Multi-Purpose Finance Bhd v Tan Sri Dato Ting Pek Khiing [1998] 7 MLJ 229; [1998] 4 MLRH 802 • Puncak Alam Housing Sdn Bhd (formerly known as Bukit Cerakah Development Sdn Bhd) v Menta Construction Sdn Bhd & Anor [2014] 1 MLJ 287; [2013] 3 MLRA 574 • CJ Century Technology Sdn Bhd v Axisjaya Sdn Bhd & Anor [2020] MLJU 2086; [2020] MLRHU 1652 • Tong Ah Poo v Jasin Construction Development (M) Sdn Bhd [2013] MLRAU 260 • PVT Enginering Sdn Bhd v Agibs Engineering & Construction Sdn Bhd & Anor [2025] CLJU 1108 • Teknojaya Construction Sdn Bhd v Telliana Plantations Sdn Bhd [2016] MLJU 1486 • Ching Yew Chye & Ors v Pavitar Singh a/l Manjeet Singh & anor [2018] 10 MLJ 612; [2017] MLRHU 1388 • National Company for Foreign Trade v Kayu Raya Sdn Bhd [1984] [1984] 1 MLRA 190; [1984] 2 MLJ 300; [1984] 1 CLJ (Rep) 283 • Cempaka Finance Bhd v Ho Lai Ying (trading as KH Trading) & Anor [2006] 2 MLJ 685 • Bank Negara Malaysia v Mohd Ismail & Ors [1992] 1 MLJ 400; [1992] 1 MLRA 190; [1992] 1 CLJ (Rep) 14 • Malaysia Airports Sdn Bhd v APFT Land Sdn Bhd [2018] 10 MLJ 257; [2018] MLRHU 1018 • Charles Greenier Sdn Bhd v Lau Wing Hong [1997] 1 CLJ 625; [1996] 2 MLRA 188; [1996] 3 MLJ 327; [1996] 3 AMR 3533 • Liebherr Sales Kluang Sdn Bhd v Zhongji Construction Sdn Bhd [2025] MLJU 257 • Order 14 Rules of Court (ROC) 2012

Practice Areas

Judges (1)

Counsel (5)

Parties (2)

Case Significance

Illustrates when a concluded settlement agreement and part-performance by the paying party defeat an attempt to resist summary judgment under Order 14 of the Rules of Court 2012 by raising previously unmentioned defects, the defendant being estopped from resurrecting complaints not raised during settlement.

This High Court decision at Kuala Lumpur concerns an application for summary judgment under Order 14 of the Rules of Court 2012 in a construction-payment dispute. The plaintiff, Kayangan Kemas Sdn Bhd, had been engaged as main contractor by the defendant, Pembinaan Kery Sdn Bhd, under a letter of acceptance in 2018 for the construction of a fifteen-storey block with a podium and a vehicle depot, the parties' contract incorporating the Agreement and Conditions of the PAM Contract 2006. The plaintiff completed the works, as evidenced by a certificate of practical completion in September 2021, and the architect issued an interim (final payment) certificate under clause 30 of the PAM Contract in the sum of RM6,982,199.58. The parties then met and reached a settlement agreement on payment of the outstanding sum, under which the defendant paid four instalments. When a balance of RM5,982,199.58 remained unpaid, the plaintiff sought summary judgment. The defendant resisted, raising various complaints about the plaintiff's works and contending that negotiations were still ongoing so that summary judgment was inappropriate. The court rejected those arguments. It held that the defendant had not raised the alleged defects after the certificate of practical completion or during the settlement negotiations, and that its conduct in actively participating in the settlement terms and paying four instalments put beyond doubt that a binding settlement agreement had been concluded, a fact the defendant did not dispute. The defendant was accordingly estopped from raising the belated complaints of defects and was bound to make good its contractual obligations. Finding no triable issue, the court entered summary judgment for the outstanding RM5,982,199.58, allowed time for payment, ordered interest at 5 per cent from the new year and awarded costs of RM5,000. The judgment illustrates when a concluded settlement agreement and part-performance defeat an attempt to resist summary judgment by raising previously unmentioned defects.

Why was summary judgment appropriate?

The court found the parties had concluded a binding settlement agreement of the outstanding sum, which the defendant did not dispute and under which it had paid four instalments; the defendant had not raised the alleged defects after practical completion or during the settlement talks, so there was no triable issue and it was estopped from raising them belatedly.

What did the court order?

The court entered summary judgment for the outstanding RM5,982,199.58, allowed the defendant time to pay, ordered interest at 5 per cent per annum from the beginning of the following year until full settlement, and awarded costs of RM5,000.

Cases Cited (14)

MY (14)
[1984] 2 MLJ 300 [1992] 1 MLJ 400 [1996] 3 AMR 3533 [1996] 3 MLJ 327 [1997] 1 CLJ 625 [1998] 4 MLRH 802 [1998] 7 MLJ 229 [2006] 2 MLJ 685 [2014] 1 MLJ 287 [2016] MLJU 1486 [2018] 10 MLJ 257 [2018] 10 MLJ 612 [2020] MLJU 2086 [2025] MLJU 257

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (wa-22ncvc-452-07-2025)