IMAGE FACADE CONSTRUCTION SDN BHD v 1. ) KETUA SETIAUSAHA KEMENTERIAN PENDIDIKAN MALAYSIA 2. ) Kerajaan Malaysia
Outcome
Berdasarkan alasan-alasan yang dihuraikan di atas, tuntutan Plaintif ditolak dan tuntutan balas D2 dibenarkan sebanyak RM25,277,397.53 dengan faedah pada kadar 5% setahun daripada tarikh penghakiman sehingga penyelesaian penuh.
Catchwords
Practice Areas
Judges (1)
Counsel (5)
Case Significance
Illustrates how the construction court resolves competing claims of lawful termination on a government building contract, allowing the Government's counterclaim where the contractor failed to prove delay was attributable to the employer.
This High Court (Construction Court) decision, delivered in Bahasa Malaysia, concerns a dispute arising from the termination of a contract for the construction of a secondary school in Selangor. Image Facade Construction Sdn Bhd, the plaintiff contractor, sued the Chief Secretary of the Ministry of Education and the Government of Malaysia (the second defendant) for a certain sum and general damages, alleging that its termination of the contract had been lawful; the Government counterclaimed for damages arising from what it said was its own lawful termination of the contract. The disputes concerned, among other things, whether delays in site possession were caused by the second defendant's failure to obtain the necessary approvals from the local authority, whether extensions of time and new completion dates had been granted, whether the plaintiff's earthworks delays flowed from an error by the second defendant in fixing the soil-disposal location, and whether the second defendant had delayed in approving certificates of delay and extension of time or failed to make progress payments in accordance with interim certificates. After a full trial, the court found that the plaintiff had failed to prove its claim on a balance of probabilities, while the second defendant had succeeded on its counterclaim. Accordingly, the court dismissed the plaintiff's claim and allowed the Government's counterclaim in the sum of RM25,277,397.53 with interest at 5% per annum from the date of judgment until full settlement. On costs, weighing the length of the trial and the number of witnesses and documents against the plaintiff's submission that a lower figure would suffice, and applying the factors in Order 59 rule 16 of the Rules of Court 2012, the court ordered the plaintiff to pay costs of RM60,000.00 to the second defendant. The judgment illustrates how the construction court allocates responsibility for delay and termination on a government building contract.
What was the outcome of the contractor's claim and the Government's counterclaim?
The court dismissed the contractor's claim, finding it unproved on a balance of probabilities, and allowed the Government's counterclaim in the sum of RM25,277,397.53 with interest at 5% per annum from the date of judgment until full settlement.
What costs were ordered?
Applying Order 59 rule 16 of the Rules of Court 2012 and weighing the length of trial and volume of evidence, the court ordered the contractor to pay costs of RM60,000.00 to the second defendant.
Cases Cited (7)
Judgment
Read the full judgment on the official Malaysia Courts portal.