EKOVEST CAPITAL SDN. BHD. (DAHULU DIKENALI SEBAGAI PROMPT CAPITAL SDN. BHD.) v 1. ) Choo Teik Shiong 2. ) GOH SEE KWONG 3. ) NG YIN CHING 4. ) YAP PEI LEE 5. ) TAN SUET FONG 6. ) YAP CHEE WEE

wa-12bncvc-30-02-2024 High Court (Mahkamah Tinggi) 9 June 2025 • WA-12BNCvC-30-02/2024 • 18 min read
27 cases cited (0 SG, 27 foreign)

Outcome

and there being no submission to the contrary by the Appellant’s counsel, I allowed the Appellant’s appeal and the Order made by the SCJ was varied in the manner as stated in paragraph 2 above. No order was made on costs.

Quoted verbatim from the judgment of High Court (Mahkamah Tinggi) (wa-12bncvc-30-02-2024). Read the full judgment on the official Malaysia Courts portal for the complete decision.

Catchwords

Practice Areas

Judges (1)

Counsel (4)

Parties (7)

Case Significance

Illustrates how the recent appellate reformulation of the starting date for liquidated ascertained damages in housing cases feeds through to the recalculation of a developer's liability to purchasers on appeal.

This High Court decision at Kuala Lumpur concerns an appeal by a housing developer against a Sessions Court judgment awarding house purchasers liquidated ascertained damages for late delivery, and it turns on the correct date from which such damages run following recent appellate authority. The purchasers had sued the developer and the Sessions Court had ordered it to pay each of them sums of liquidated ascertained damages, together with interest at 10 per cent per annum calculated from a specified date and costs. The developer appealed, contending among other things that the purchasers' claim was time-barred under section 6 of the Limitation Act 1953, that the principles in the well-known Federal Court decision in Ang Ming Lee were distinguishable on the facts, that the purchasers had failed to challenge an extension of time by judicial review, that they were estopped and would be unjustly enriched by claiming additional damages, and that they had not satisfied the parol evidence rule under section 91 of the Evidence Act 1950. The central issue that determined the appeal, however, was the correct starting point for the calculation of the liquidated ascertained damages. During the hearing the parties' submissions addressed the impact of recent Federal Court authority on the point, and the developer's counsel ultimately conceded that the damages should be calculated in accordance with the position reflected in that authority, which fixed the relevant starting point by reference to the date of the booking fee. The court, being inclined to the view that the purchasers' revised computation reflected the correct legal position following the recent decisions and there being no submission to the contrary, allowed the developer's appeal and varied the Sessions Court's order, substituting reduced sums payable to each of the purchasers. No order was made as to costs. The judgment is a useful illustration of how the recent appellate reformulation of the starting date for liquidated ascertained damages in housing cases feeds through to the recalculation of a developer's liability on appeal.

Summary

Six purchasers of residential units at the EkoCheras project claimed liquidated ascertained damages for late delivery against the developer Ekovest Capital. The High Court allowed the developer's appeal in part, varying the Sessions Court's award to recalculate LAD from the date of booking fee until the date of SPA, in line with the Federal Court's decision in Obata Ambak, significantly reducing the amounts payable.

What was the decisive issue on the developer's appeal?

The decisive issue was the correct date from which the liquidated ascertained damages for late delivery should run; following recent Federal Court authority, the starting point was fixed by reference to the date of the booking fee, a position the developer's counsel ultimately conceded reflected the correct law.

How did the court dispose of the appeal?

The court allowed the developer's appeal and varied the Sessions Court's order, substituting reduced sums of liquidated ascertained damages payable to each of the purchasers in line with the corrected computation, and made no order as to costs.

Statutes Cited

Courts of Judicature Act 1964
s 29

Cases Cited (27)

MY (27)
[1984] 2 MLJ 165 [1988] 2 MLJ 170 [1995] 2 MLJ 597 [2003] 2 CLJ 19 [2003] 2 MLJ 97 [2004] 4 CLJ 309 [2005] 2 MLJ 1 [2008] 2 CLJ 284 [2008] 2 MLJ 87 [2009] 6 CLJ 626 [2009] 6 MLJ 1 [2010] 3 CLJ 377 [2010] 3 MLJ 509 [2012] 4 MLJ 149 [2012] 6 MLJ 1 [2013] 4 MLJ 693 [2015] 2 MLJ 441 [2016] 2 MLJ 428 [2017] 5 CLJ 58 [2020] 1 CLJ 162 [2020] 1 MLJ 281 [2020] 12 MLJ 67 [2021] 2 MLJ 60 [2024] 5 MLJ 417 [2024] 5 MLJ 897 [2024] MLJU 2399 [2025] AMEJ 1247

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (wa-12bncvc-30-02-2024)