KENWINGSTON SDN. BHD. v INGCA SDN. BHD.

wa-12bc-6-06-2024 High Court (Mahkamah Tinggi) 2 October 2025 • WA-12BC-6-06/2024 • 21 min read
9 cases cited (0 SG, 9 foreign)

Outcome

The order of the Sessions Court dated 5.6.2024 is hereby set aside, and the Plaintiff’s claim is dismissed. Costs of this Appeal and of the proceedings below are awarded to the Defendant, subject to allocatur.

Quoted verbatim from the judgment of High Court (Mahkamah Tinggi) (wa-12bc-6-06-2024). Read the full judgment on the official Malaysia Courts portal for the complete decision.

Catchwords

Practice Areas

Judges (1)

Counsel (4)

Parties (2)

Case Significance

Instructive on the limits of a section 71 Contracts Act 1950 restitutionary claim against a paying party in a multi-tier construction chain, holding that a party that has already given full consideration for the benefit is not unjustly enriched despite the absence of privity.

This High Court decision at Kuala Lumpur, in the Construction Court, is an appeal from the Sessions Court concerning a claim by a supplier down a construction contracting chain against a party with whom it had no contract. The appellant, Kenwingston Sdn Bhd, was the principal subcontractor for a housing development, engaged by the main contractor which was in turn appointed by the developer. The principal subcontractor engaged a subcontractor for plumbing works, and that subcontractor engaged the respondent, Ingca Sdn Bhd, as a sub-subcontractor to supply and install fibreglass-reinforced plastic water tanks. When the subcontractor failed to pay the sub-subcontractor, the sub-subcontractor sued the principal subcontractor, and the Sessions Court allowed its claim of RM847,484.12 with interest and costs, relying on section 71 of the Contracts Act 1950, which imposes an obligation to pay for a non-gratuitous benefit lawfully enjoyed. The principal subcontractor appealed. The court, per Rajes Raghavji JC, held that there was no privity of contract between the principal subcontractor and the sub-subcontractor, and that the Sessions Court had erred in invoking section 71 against the principal subcontractor. The decisive point was that the principal subcontractor had already provided full consideration for the works, including the water tanks, having paid down the contractual chain for the benefit it received; it was therefore not unjustly enriched at the sub-subcontractor's expense, and to compel it to pay again would sanction an inequitable double payment. Although the court accepted that a claim under section 71 is independent and that the sub-subcontractor had not acted gratuitously, that became academic once the principal subcontractor had shown it was not unjustly enriched. The appeal was allowed, the Sessions Court order set aside and the claim dismissed, with costs to the principal subcontractor. The judgment is instructive on the limits of a section 71 restitutionary claim against a paying party in a multi-tier construction chain where privity is absent.

Could the sub-subcontractor recover from the principal subcontractor under section 71 of the Contracts Act 1950?

No. The court held there was no privity between them and that section 71 did not apply, because the principal subcontractor had already paid full consideration down the contracting chain for the benefit it received, including the water tanks, and so was not unjustly enriched; compelling it to pay again would sanction an inequitable double payment.

What was the outcome of the appeal?

The appeal was allowed, the Sessions Court's order awarding the sub-subcontractor RM847,484.12 was set aside, and the claim was dismissed with costs to the principal subcontractor.

Statutes Cited

Cases Cited (9)

UK (1)
[1936] 2 KB 403
MY (8)
[1967] 1 MLJ 211 [1979] 1 MLJ 120 [2014] 8 MLJ 14 [2015] 9 CLJ 1002 [2018] 9 CLJ 26 [2018] MLJU 1323 [2020] 10 CLJ 1 [2025] 4 CLJ 761

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (wa-12bc-6-06-2024)