MTC ENGINEERING SDN. BHD. v VME PROCESS ASIA PACIFIC PTE. LTD.
Outcome
We dismiss the appeal. By agreement, we order parties to bear own costs.
Catchwords
Practice Areas
Judges (3)
Counsel (5)
Case Significance
Confirms that a non-party to a contract cannot invoke its arbitration clause simply because a separate agreement it signed refers to that contract: incorporation by reference under section 9(5) of the Arbitration Act 2005 requires more than a bare reference, and a letter of undertaking without its own arbitration clause does not attract a stay.
This Court of Appeal decision concerns whether a party can invoke an arbitration clause contained in a main contract to which it is not a party, merely because a separate agreement to which it is a party refers to that main contract. The respondent, a Singapore company supplying oil-and-gas topside processing modules, had entered into an engineering, procurement, construction and pre-commissioning contract with a subsidiary of the appellant, MTC Engineering Sdn Bhd, for a field development project; clause 44.2 of that contract provided for binding arbitration in Singapore under the SIAC Rules. On the same day, the appellant issued a letter of undertaking in favour of the respondent, assuming all payment obligations under the main contract so that its obligations mirrored those of its subsidiary; the letter of undertaking contained no arbitration clause but was attached to the main contract as an appendix. When the respondent sued the appellant in the High Court, the appellant sought a stay under section 10 of the Arbitration Act 2005, contending that the arbitration agreement in the main contract had been incorporated by reference into the letter of undertaking. The Senior Assistant Registrar granted the stay, but the High Court overturned it, and the appellant appealed. The Court of Appeal held that the appellant, not being a party to the main contract, could not invoke its arbitration clause merely by the reference in the letter of undertaking, and that the requirements for incorporation by reference under section 9(5) of the Arbitration Act 2005 were not satisfied. It agreed with the High Court that a Federal Court authority relied on by the appellant was not relevant, since that case concerned the procedural requirements for recognising an arbitral award under section 38 and did not decide whether an arbitration agreement had been incorporated by reference. Finding no appealable error in the High Court's decision, the court dismissed the appeal and, by agreement, ordered the parties to bear their own costs.
Summary
MTC Engineering sought to invoke an arbitration clause in a contract between VME Process Asia Pacific and MTC's subsidiary SOM, to which MTC was not a party. The Court of Appeal dismissed the appeal, holding that a non-party cannot invoke an arbitration agreement merely by reference to the main contract in a separate Letter of Undertaking, and the arbitration clause was not incorporated by reference under section 9(5) of the Arbitration Act 2005.
What was the central issue on the appeal?
Whether the appellant, which was not a party to the main contract containing the arbitration clause, could invoke that arbitration agreement to obtain a stay merely because a separate letter of undertaking to which it was a party referred to the main contract.
How did the court resolve the incorporation-by-reference question?
It held that a mere reference in the letter of undertaking did not incorporate the main contract's arbitration clause, and that the requirements for incorporation by reference under section 9(5) of the Arbitration Act 2005 were not satisfied, so the appellant could not invoke the arbitration agreement.
What was the outcome?
Finding no appealable error in the High Court's refusal of a stay, the Court of Appeal dismissed the appeal and, by agreement, ordered the parties to bear their own costs.
Statutes Cited
Cases Cited (3)
Judgment
Read the full judgment on the official Malaysia Courts portal.
Read on eJudgmentSource: eJudgment (w-03imncc-1-01-2024)