XXXX v Fairview International School Nusajaya Sdn Bhd
Catchwords
Practice Areas
Counsel (5)
Case Significance
Illustrates how a valid completion certificate operates as a precondition to a contractor's entitlement to payment, and appellate deference to a trial court's findings on delay, liquidated damages and the absence of certification in a construction dispute.
This Court of Appeal decision, in which Azmi bin Ariffin JCA delivered the grounds, arises from a construction dispute over the installation of lifts at an international school. The respondent school, as plaintiff, had sued the appellant lift contractor, as defendant, and after a full trial the High Court allowed the school's claim, awarding liquidated ascertained damages of RM940,000 for a delay of 94 days at the contractual rate of RM10,000 per day, together with further sums, while dismissing the contractor's counterclaim. The contractor appealed against that decision. The issues included a discrepancy between the letter of award and other contract documents, the absence of any written notice seeking an extension of time, the unwarranted delay in completing the works, the costs of rectification and safety works carried out by a third party, the school's loss of income from student intake, and the contractor's counterclaim for payment said to be due.
A central question was whether the consultant engaged on the project had issued a valid certification that the lift works had been completed in accordance with the contract, so as to entitle the contractor to payment. The High Court had found that there was no valid certification of completion issued by the consultant, that the contractor's counterclaim therefore could not be sustained, and that the rectification and safety works completed through the third party should be allowed to the school, so that the contractor's assertion that the school had breached the letter of award was untenable.
The Court of Appeal, after carefully scrutinising the notes of proceedings and the submissions, found no merit in the appeal. It agreed with the trial judge that there had been no certification by the consultant that the lift works were completed as required by the contract, affirmed the High Court's decision, and ordered the appellant to pay the respondent costs of RM25,000 subject to allocatur. The judgment is a useful illustration of how a valid completion certificate operates as a precondition to a contractor's entitlement to payment, and of appellate deference to a trial court's findings on delay, liquidated damages and the absence of certification in a construction dispute.
Summary
MS Elevators Engineering appealed the High Court's decision awarding Fairview International School RM940,000 in liquidated damages for 94 days delay in installing three lifts, plus RM70,294.80 in rectification costs and RM35,000 nominal damages for lost student fees. The Court of Appeal dismissed the appeal, finding no merits and affirming that the defendant was not entitled to payment without a valid certification from the consultant.
Why was the contractor's appeal dismissed?
The Court of Appeal found no merit in the appeal, agreeing with the trial judge that the project consultant had issued no valid certification that the lift works were completed in accordance with the contract, so the contractor's counterclaim for payment could not be sustained, and it affirmed the High Court's award of liquidated ascertained damages to the school.
What did the Court order on the appeal?
It affirmed the High Court's decision, dismissed the appeal, and ordered the appellant to pay the respondent costs of RM25,000 subject to allocatur, leaving intact the award of RM940,000 in liquidated ascertained damages for the 94-day delay and the dismissal of the contractor's counterclaim.
Statutes Cited
Cases Cited (4)
Judgment
Read the full judgment on the official Malaysia Courts portal.
Read on eJudgmentSource: eJudgment (w-02ncvcw-18-01-2022)