PENS HOLDINGS SDN. BHD. v AIMA CONSTRUCTION SDN. BHD.

ra-12bncc-1-12-2024 High Court (Mahkamah Tinggi) 11 December 2025 • RA-12BNCC-1-12/2024 • 18 min read
38 cases cited (0 SG, 38 foreign)

Outcome

Rayuan perayu adalah dengan ini ditolak dengan kos sebanyak RM10,000.00.

Quoted verbatim from the judgment of High Court (Mahkamah Tinggi) (ra-12bncc-1-12-2024). Read the full judgment on the official Malaysia Courts portal for the complete decision.

Catchwords

Practice Areas

Judges (1)

Counsel (4)

Parties (2)

Case Significance

Illustrates how a main contractor's written assurance to a downstream sub-contractor can be examined for the ingredients of a constructive trust over retention monies within a layered construction-contracting chain, and the limited scope for appellate interference with the trial court's findings on such a trust.

This High Court decision at Kangar, Perlis, is an appeal from the Sessions Court in a construction-payment dispute. The project was the construction of the Perlis State Legislative Assembly Complex, for which the appellant, Pens Holdings Sdn Bhd, had been awarded the main contract by the Public Works Department (JKR) in about 2005. The appellant appointed Felhatan Trading Sdn Bhd as sub-contractor, which in turn engaged a firm trading as Nam Fang Kusyen dan Perhiasan, which appointed the respondent, Aima Construction Sdn Bhd, as its sub-contractor by a letter dated 19 May 2005. The respondent completed the works in September 2007, a certificate of completion issued, and the defects liability period expired in September 2009, but a retention sum of RM331,665.17 remained unpaid, in respect of which the respondent had earlier obtained judgment against the Nam Fang firm. The present dispute focused on a letter the appellant had sent the respondent in January 2016. The Sessions Court had allowed the respondent's claim for the retention sum with interest at 5 per cent from 15 September 2009 and costs. On appeal the central question was whether that letter created a constructive trust binding the appellant in favour of the respondent, and whether any such constructive trust was subject to a further approval letter from a third party. Having examined the correspondence and the findings below, the High Court found no basis to disturb the Sessions Judge's conclusions on the existence and effect of the trust. It dismissed the appeal and ordered costs of RM10,000. In upholding the finding, the court accepted that the January 2016 letter had to be read against the full contracting chain and the earlier judgment obtained against the intermediate firm, rather than in isolation. The judgment is a useful illustration of how a contractor's written assurance to a downstream sub-contractor can be scrutinised for the ingredients of a constructive trust over retention monies in a layered construction-contracting chain.

Summary

A sub-contractor sued the main contractor for RM331,665.17 in retention money for works on the Perlis State Assembly Complex project, relying on a letter creating a constructive trust. The High Court dismissed the appeal, affirming the Sessions Court's finding that the main contractor's letter constituted a constructive trust obligation to pay the sub-contractor directly, regardless of the approval condition and absence of privity of contract.

What was the issue on appeal?

Whether a letter the appellant main contractor sent the respondent sub-contractor in January 2016 created a constructive trust binding the appellant in favour of the respondent over an unpaid retention sum of RM331,665.17, and whether any such trust was subject to a further third-party approval letter.

How did the court decide the appeal?

The court found no basis to disturb the Sessions Judge's findings on the existence and effect of the constructive trust, dismissed the appeal, and ordered costs of RM10,000, leaving intact the award of the retention sum with interest at 5 per cent from 15 September 2009 and costs.

Cases Cited (38)

UK (15)
[1893] 2 QB 390 [1923] 2 Ch 533 [1929] 2 Ch 213 [1948] 2 All ER 133 [1968] 1 WLR 1555 [1968] 2 All ER 1073 [1972] 1 WLR 1286 [1972] 3 All ER 744 [1975] 1 WLR 1338 [1975] 3 All ER 768 [1978] 1 All ER 382 [1978] 1 WLR 93 [1980] 1 All ER 393 [1982] 1 WLR 1044 [1982] 2 All ER 953
MY (23)
[1984] 2 MLJ 165 [2003] 2 CLJ 19 [2003] 2 MLJ 97 [2004] 4 CLJ 309 [2005] 2 MLJ 1 [2008] 2 CLJ 284 [2008] 2 MLJ 87 [2009] 6 CLJ 626 [2009] 6 MLJ 1 [2010] 3 CLJ 377 [2010] 3 MLJ 509 [2012] 4 MLJ 149 [2013] 4 MLJ 693 [2013] 5 CLJ 949 [2014] 4 MLJ 64 [2015] 1 CLJ 309 [2016] 2 MLJ 861 [2016] 8 CLJ 211 [2016] 9 CLJ 73 [2017] 5 CLJ 58 [2017] MLJU 1107 [2018] 7 CLJ 235 [2999] 2 CLJ 886

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (ra-12bncc-1-12-2024)