1. ) ANUAR BIN MAHMOOD 2. ) FARIDAH BINTE AHMAD v JOHOR LAND BERHAD

ja-22c-4-06-2020 High Court (Mahkamah Tinggi) 13 January 2026 • JA-22C-4-06/2020 • 77 min read
27 cases cited (0 SG, 27 foreign)

Outcome

In the circumstances, this Court makes the following orders – (a) the Plaintiffs' claim is allowed in part.

Quoted verbatim from the judgment of High Court (Mahkamah Tinggi) (ja-22c-4-06-2020). Read the full judgment on the official Malaysia Courts portal for the complete decision.

Catchwords

Practice Areas

Judges (1)

Counsel (4)

Parties (3)

Case Significance

Illustrates a purchaser's remedies for a defective house under a Housing Development Act sale and purchase agreement — liquidated ascertained damages, repair costs, loss of use and damages for distress — and that a concurrent negligence claim does not enlarge recovery where the contractual remedies are adequate.

This High Court decision at Johor Bahru concerns a claim by two purchasers against a housing developer, Johor Land Berhad, arising from the sale of a double-storey terrace house at Bandar Dato' Onn, Johor Bahru, for RM629,300.00 under a sale and purchase agreement dated 9 February 2012. The purchasers alleged that the property was delivered with serious defects and, despite multiple rectification attempts by the developer, remained uninhabitable more than ten years after vacant possession. They claimed general damages for breach of contract, the cost of repairs, loss of use or rental, liquidated ascertained damages for late delivery, and interest and costs. The developer, licensed under the Housing Development (Control and Licensing) Act 1966, denied the claims, contending that the property had been completed in accordance with approved plans, that a certificate of completion and compliance had issued, that the purchasers had obstructed rectification works, and that they had failed to mitigate their losses.

After a trial spread over five days, the court considered the statutory scheme and the SPA terms, including the provisions on defects and liquidated damages, and the question — on which it sought further submissions — whether the purchasers' refusal to permit rectification was justified by safety concerns. It also addressed the developer's concurrent liability in negligence, holding that the contractual remedies under the SPA adequately compensated the purchasers and that the tort claim did not increase the recoverable damages.

The court entered judgment for the purchasers for RM691,294.52, comprising liquidated ascertained damages of RM63,594.52, repair and rectification costs of RM339,700.00, loss of use or rental of RM250,000.00, a consultant fee of RM8,000.00 and RM30,000.00 for distress and inconvenience. The claim for aggravated and exemplary damages was dismissed, as was a purported set-off for unpaid utility deposits that had not been pleaded. Interest was awarded and costs of RM150,000.00. The judgment is a detailed illustration of a purchaser's remedies for defective delivery under a housing SPA.

Summary

Singaporean plaintiffs purchased a terrace house in Bandar Dato' Onn, Johor Bahru from developer Johor Land Berhad for RM629,300, but the property was delivered with serious defects including electrical problems and remained uninhabitable for over 10 years. The key issues included breach of contract under the SPA, the developer's defence that the plaintiffs obstructed rectification, and the duty to mitigate losses. The High Court allowed the claim in part, awarding RM691,294.52 comprising LAD, repair costs, loss of use, consultant fees and distress damages.

What damages did the court award the purchasers?

The court entered judgment for RM691,294.52, made up of liquidated ascertained damages of RM63,594.52, repair and rectification costs of RM339,700.00, loss of use or rental of RM250,000.00, a consultant fee of RM8,000.00 and RM30,000.00 for distress and inconvenience, together with interest and costs of RM150,000.00. The claim for aggravated and exemplary damages was dismissed.

How did the court treat the concurrent claim in negligence?

The court held that the contractual remedies under the sale and purchase agreement adequately compensated the purchasers and that the concurrent claim in tort did not increase their recoverable damages, so the recovery was measured by the contractual entitlement.

Statutes Cited

Cases Cited (27)

UK (8)
[1919] 2 KB 581 [1964] AC 1129 [1966] 2 All ER 901 [1980] 1 WLR 433 [1990] 2 AC 605 [1990] 2 All ER 908 [1991] 1 WLR 1421 [2001] UKHL 49
MY (19)
[1969] 2 MLJ 6 [1982] 2 MLJ 31 [1984] 1 MLJ 283 [1987] 1 MLJ 304 [1994] 3 MLJ 777 [1995] 1 MLJ 817 [1995] 2 MLJ 663 [2003] 1 MLJ 567 [2006] 2 MLJ 389 [2008] 4 MLJ 852 [2009] 4 MLJ 445 [2015] 4 MLJ 734 [2019] 6 MLJ 15 [2021] 2 MLJ 60 [2021] 3 MLJ 365 [2021] MLJU 140 [2022] 3 MLJ 135 [2024] 2 MLJ 652 [2025] 12 MLJ 21

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (ja-22c-4-06-2020)