FOONG LI TRADING SDN BHD v OCR PROPERTIES (KUANTAN) SDN BHD
Catchwords
Practice Areas
Judges (1)
Counsel (6)
Case Significance
Instructive on the mandatory notice requirement under section 30(2) of the Construction Industry Payment and Adjudication Act 2012 and the evidential burden on a principal resisting a sub-contractor's direct-payment claim after the main contractor's default.
This High Court decision at Shah Alam concerns an application under section 30 of the Construction Industry Payment and Adjudication Act 2012 for an order that an adjudicated amount be paid directly by the principal. The plaintiff, Foong Li Trading Sdn Bhd, was a sub-contractor engaged by a main contractor, Kencana Amanjaya Sdn Bhd, on a project for which the defendant, OCR Properties (Kuantan) Sdn Bhd, was the principal. The plaintiff carried out its works but was not fully paid; after the main contractor was wound up, the plaintiff obtained leave under section 471(2) of the Companies Act 2016 to pursue adjudication against it and secured an adjudication decision requiring payment of an outstanding sum together with interest and the costs of the adjudication. The decision remaining unpaid, the plaintiff served a notice on the defendant, as principal, requesting direct payment under section 30, and the defendant replied that no monies were due or payable to the main contractor, relying on settlement agreements it had entered into with the main contractor. The court, per Shahriza Zalina binti Abdul Shukor JC, allowed the application. Drawing on the Court of Appeal in Kinu Sdn Bhd, it held that section 30(2), by its use of 'shall', imposes a mandatory requirement that upon receiving the sub-contractor's written request the principal must serve a written notice on the main contractor against whom the adjudication decision was obtained, requiring proof of payment, and that a failure to do so is a factor in determining whether money is due or payable from the principal to the main contractor and may even justify an adverse inference under section 114(g) of the Evidence Act 1950. Having failed to serve such a notice, the defendant had to satisfy the court, on independent, credible and cogent evidence, that no amount was due or payable to the main contractor, and the court found it had failed to discharge that evidential burden. The application was accordingly allowed with costs of RM7,500. The judgment is instructive on the mandatory notice requirement and the evidential burden on a principal resisting a section 30 direct-payment claim.
What is the effect of a principal's failure to serve the notice required by section 30(2)?
The court held, following Kinu Sdn Bhd, that section 30(2) mandatorily requires the principal, on receiving the sub-contractor's request, to serve a written notice on the main contractor requiring proof of payment; a failure to do so is a factor in deciding whether money is due to the main contractor and may justify an adverse inference under section 114(g) of the Evidence Act 1950, and the principal must then independently prove that nothing is due.
Why was the plaintiff's section 30 direct-payment application allowed?
The court found that the defendant principal had failed to serve the mandatory section 30(2) notice on the main contractor and had failed to satisfy the court on independent, credible and cogent evidence that no amount was due or payable to the main contractor, so it had not discharged its evidential burden; the application was allowed with costs of RM7,500.
Statutes Cited
Cases Cited (3)
Judgment
Read the full judgment on the official Malaysia Courts portal.
Read on eJudgmentSource: eJudgment (ba-24c-27-05-2025)