DNeX SOLUTIONS SDN BHD v I DATA CENTRE SOLUTIONS SDN BHD

ba-22ncvc-16-01-2023 High Court (Mahkamah Tinggi) 21 August 2025 • BA-22NCvC-16-01/2023 • 14 min read
4 cases cited (0 SG, 4 foreign)

Outcome

For the reasons set out above, the Plaintiff’s claim is allowed and the Defendant’s counterclaim is dismissed with costs RM20,000.00.

Quoted verbatim from the judgment of High Court (Mahkamah Tinggi) (ba-22ncvc-16-01-2023). Read the full judgment on the official Malaysia Courts portal for the complete decision.

Catchwords

Practice Areas

Judges (1)

Counsel (5)

Parties (2)

Case Significance

Illustrates the operation of frustration and restitution under sections 57 and 66 of the Contracts Act 1950, and the burden on a party that has received money under a frustrated contract to prove the expenses it says justify retaining that money.

This High Court decision at Shah Alam concerns a claim for restitution of money paid under a subcontract for a large government project, and the effect of frustration on the parties' obligations. The plaintiff had won a substantial contract to develop a new data centre for a government agency and to relocate existing infrastructure, and had subcontracted part of the works to the defendant. It later sued to recover a sum of RM5,789,878.95 it had paid the defendant, contending that the defendant had not performed and had thereby been unjustly enriched, and relying on sections 66 and 71 of the Contracts Act 1950. The defendant maintained that the contract remained on foot, that the money had already been expended on preliminary works, and counterclaimed for further sums said to have been paid to consultants. A central feature of the case was that the location of the project site had changed, and the court analysed whether this had frustrated the contract, rendering performance of the original bargain impossible or radically different under section 57 of the Contracts Act 1950. The court found that there was no basis for rescission of the contract from the outset, but that the change of site had frustrated it. Where a contract is frustrated, the party who has received an advantage must make restitution, and a party claiming to set off its expenses bears the burden of proving them. The court held that the defendant had failed to discharge the burden of proving the value of any work done or advantage conferred, so that it could not retain the sum paid. It allowed the plaintiff's claim for restitution and dismissed the counterclaim, with costs of RM20,000. The judgment illustrates the operation of frustration and restitution under sections 57 and 66 of the Contracts Act 1950, and the burden on a party seeking to justify retention of money by reference to expenses incurred.

What effect did the change of project site have?

The court held that the change in the location of the project site frustrated the contract under section 57 of the Contracts Act 1950, rendering the original bargain radically different, although there was no basis for rescinding the contract from the outset.

Why was the plaintiff's restitution claim allowed?

Where a contract is frustrated, a party who has received an advantage must make restitution, and a party seeking to set off its expenses must prove them. The defendant failed to discharge the burden of proving the value of any work done, so it could not retain the sum paid; the claim was allowed and the counterclaim dismissed with costs of RM20,000.

Statutes Cited

Cases Cited (4)

UK (1)
[1956] AC 696
MY (3)
[1970] 1 MLJ 138 [2007] 4 MLJ 201 [2010] 1 CLJ 269

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (ba-22ncvc-16-01-2023)