MODKHA MARINE SDN. BHD. v RAIN INTERNATIONAL SDN. BHD.

ba-22ncvc-103-03-2024 High Court (Mahkamah Tinggi) 22 January 2025 • BA-22NCvC-103-03/2024 • 8 min read
3 cases cited (0 SG, 3 foreign)

Outcome

Keputusan [27] Bersandarkan alasan di atas, saya dapati permohonan ini tidak berasas dan tidak wajar dibenarkan. Oleh itu, permohonan Plaintif di Lampiran 28 dengan ini ditolak dengan kos sebanyak RM1000 kepada Defendan (tertakluk kepada fi alokator).

Quoted verbatim from the judgment of High Court (Mahkamah Tinggi) (ba-22ncvc-103-03-2024). Read the full judgment on the official Malaysia Courts portal for the complete decision.

Catchwords

Practice Areas

Judges (1)

Counsel (5)

Parties (2)

Case Significance

Confirms that once a stay for arbitration under section 10 of the Arbitration Act 2005 is granted and left unchallenged, a party cannot use an interlocutory application to reroute the dispute into court-directed mediation, and such an attempt may be treated as an abuse of process.

This High Court decision at Shah Alam addresses what a party may and may not do after proceedings have been stayed in favour of arbitration. Earlier, on 25 June 2024, the court had stayed the action pending reference of the dispute to arbitration, on finding that the parties' agreement contained an arbitration clause and that the defendant had not taken any step in the proceedings, so that a stay under section 10 of the Arbitration Act 2005 was warranted. That stay order was neither appealed nor set aside by the plaintiff. Some months later, however, the plaintiff filed an application asking the court to direct the parties to undertake mediation to finalise the arbitration agreement or to determine the dispute that was the subject matter of the action.

The court refused the application. It reasoned that, the matter having been stayed for arbitration, the plaintiff was obliged to commit to complying with the procedural requirements of the arbitral institution, and that a reference to arbitration is mandatory once the relevant requirements have been met. While the court remained seised of a supervisory or monitoring role because the case retained a pending status and was not yet functus officio, it regarded the plaintiff's fresh application as, in substance, an abuse of the court's process — an attempt to divert the matter away from the arbitration the plaintiff had not challenged. The court added that the parties remained free to negotiate a consensual settlement if both were willing, since the very purpose of arbitration is to resolve the dispute, but any such course required mutual agreement.

The court dismissed the plaintiff's application with costs of RM1,000, subject to allocator. The judgment illustrates that once a stay for arbitration is granted and left unchallenged, a party cannot use an interlocutory application to reroute the dispute into court-directed mediation, and such an attempt may be treated as an abuse of process.

Why had the proceedings been stayed?

On 25 June 2024 the court stayed the action under section 10 of the Arbitration Act 2005, having found the parties' agreement contained an arbitration clause and the defendant had taken no step in the proceedings; that stay was not appealed or set aside.

What did the plaintiff later apply for, and how did the court respond?

The plaintiff applied for a direction that the parties undertake mediation to finalise the arbitration agreement or determine the dispute; the court refused, holding the plaintiff must commit to the arbitral procedure and treating the application as an abuse of process.

What was the outcome?

The court dismissed the application with costs of RM1,000 subject to allocator, while noting the parties remained free to settle consensually if both agreed.

Cases Cited (3)

UK (1)
[1939] 1 All ER 95
MY (2)
[2013] MLJ 123 [2020] 4 CLJ 301

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (ba-22ncvc-103-03-2024)