TECT HUAT DEVELOPMENT SDN BHD v 1. ) GOH CHENG HUAT 2. ) GOH CHENG HUAY 3. ) GOH CHING CHAI 4. ) GOH CHING ENG 5. ) GOH CHING SEONG
Outcome
| P a g e [24] In the circumstances, we find merits in Appeal 353 and the appeal is allowed and the High Court Order dated 29 January 2024, to the extent where it ordered the Defendants to pay RM421,113.25 to the Plaintiff and upon such payment the 25 individual titles are to be released to the Defendants, is hereby set aside. We make a Consequential Order that the sum of RM421,113.25 with all interest accrued thereon, presently held by the Defendants solicitors Messrs.
Catchwords
Practice Areas
Judges (3)
Counsel (9)
Case Significance
Illustrates that a contracting party asserting an extension of time must prove the signatory's authority to bind the others, and the principle that a monetary order against a defendant cannot stand once the claim that would support it has been dismissed.
This decision of the Court of Appeal disposes of two consolidated appeals arising from a joint-venture dispute between a developer, Tect Huat Development Sdn Bhd, and a group of landowners who were the defendants in the High Court. This appeal (Appeal 352) is the developer's appeal against the dismissal of its claim, which had alleged unlawful termination of a Joint Venture Agreement dated 24 March 2014 and a Supplementary Agreement dated 13 September 2018. The pivotal question was whether there had been a valid extension of time of 30 months to complete the project, and that in turn depended on whether one of the defendants had ostensible authority to sign the Supplementary Agreement — a document handed to him at a meeting and later signed and transmitted to the developer by WhatsApp in November 2018.
The Court of Appeal examined the evidence surrounding the signing and circulation of the Supplementary Agreement and concluded that it did not establish a valid extension of time of 30 months. The developer could not show that the defendant who signed the document had the ostensible authority to bind the other landowners to the extension, so the extension on which the developer's case depended was not made out. Because the developer's claim therefore failed, the Court of Appeal found no merit in Appeal 352 and dismissed it with costs. In the companion appeal it went further, holding that the High Court had erred in assessing damages and ordering the defendants to pay a sum to the developer once the developer's claim had been dismissed, since with the claim gone there was no foundation for a money order and no evidence had been led to support a quantum meruit or an implied term of reimbursement. The judgment illustrates the centrality of authority to bind co-contracting parties, and the principle that no monetary relief can survive the dismissal of the claim that would support it.
Summary
Tect Huat Development, a property developer, challenged the landowners' termination of a joint venture agreement for residential and commercial development in Kuala Langat, claiming one co-owner had granted an extension of time via WhatsApp. The Court of Appeal dismissed the developer's appeal, finding that the co-owner lacked ostensible authority to bind all five landowners. The landowners' cross-appeal was allowed, setting aside a RM421,113.25 payment order and ordering release of all 25 individual land titles to them.
Why was the developer's appeal dismissed?
The developer's claim depended on there having been a valid 30-month extension of time, which turned on whether the defendant who signed the Supplementary Agreement had ostensible authority to bind the other landowners. The Court of Appeal found the evidence did not establish such authority or a valid extension, so the claim failed and Appeal 352 was dismissed with costs.
What did the court say about the money order the High Court had made?
In the companion appeal the court held that once the developer's claim was dismissed there was no basis for ordering the defendants to pay it any sum; that order was a nullity because no evidence had been led to support a quantum meruit or an implied term of reimbursement. Monetary relief could not survive the dismissal of the claim that would have supported it.
Cases Cited (6)
Judgment
Read the full judgment on the official Malaysia Courts portal.
Read on eJudgmentSource: eJudgment (b-02ncvcw-352-03-2024)