MAYFAIR VENTURES SDN BHD v SETIAKON BUILDERS SDN BHD

b-02ca-2178-12-2024 Court of Appeal (Mahkamah Rayuan) 28 September 2025 • B-02(C)(A)-2178-12/2024 • 49 min read
12 cases cited (1 SG, 11 foreign)

Outcome

As for Mayfair’s appeal in Appeal No. 2185 we allowed the appeal in part. We vary the amount ordered under the said enforcement application on the same terms as per Appeal No. 2178. [74] Costs of RM20,000 for each appeal to be paid by Setiakon to Mayfair subject to allocator.

Quoted verbatim from the judgment of Court of Appeal (Mahkamah Rayuan) (b-02ca-2178-12-2024). Read the full judgment on the official Malaysia Courts portal for the complete decision.

Catchwords

Practice Areas

Judges (3)

Counsel (7)

Parties (2)

Case Significance

Instructive on the jurisdictional limits of an adjudicator under the Construction Industry Payment and Adjudication Act 2012, holding that a stand-alone late-payment interest claim on settled certificates falls outside the definition of a 'payment' and that setting aside under section 15 is confined to jurisdiction and natural justice.

This Court of Appeal decision concerns the jurisdiction of an adjudicator under the Construction Industry Payment and Adjudication Act 2012 and, in this appeal, an application to set aside an adjudication decision under section 15 of the Act. The appellant, Mayfair Ventures Sdn Bhd, appealed against the High Court's dismissal of its originating summons to set aside an adjudication decision obtained by the respondent, Setiakon Builders Sdn Bhd, the main contractor under a letter of award incorporating a PAM form of contract. This appeal was heard together with a related appeal concerning enforcement of the same adjudication decision, and the two were decided in a single judgment. The central question was whether the adjudicator had acted in excess of jurisdiction by allowing a component of the respondent's claim, in circumstances where an adjudicator's jurisdiction under section 27(1) is limited to the matter referred to adjudication, and a payment claim must fall within the definition of 'payment' in section 4 of the Act. The court, comprising Azmi bin Ariffin, Mohd Firuz bin Jaffril and Ong Chee Kwan JJCA, distinguished two parts of the respondent's claim. The first was a claim for pure late-payment interest on work done under certificates that had already been fully settled; the court held that a claim for late-payment interest standing alone does not fit the definition of a 'payment' under section 4, so that by allowing it the adjudicator had exceeded her jurisdiction. The second part, a claim for work done and interest under other certificates, disclosed no appealable error. Emphasising that at this stage the court was not concerned with the merits of the adjudicator's decision, which could be set aside only on the grounds of excess or lack of jurisdiction or a denial of natural justice under section 15, the court allowed the appeal in part, deducting the sum of RM1,610,732.87 from the amount awarded, so that the respondent was to refund that sum plus interest of RM95,176.42, with costs of RM20,000. The judgment is instructive on the jurisdictional limits of adjudication and on whether a stand-alone late-payment interest claim falls within the statutory definition of a payment.

Summary

Mayfair Ventures appealed the High Court's refusal to set aside a CIPAA adjudication decision in favour of contractor Setiakon Builders, raising the issue of whether the adjudicator exceeded her jurisdiction by allowing a claim for late payment interest on fully settled progress certificates. The Court of Appeal allowed the appeal in part, finding that the claim for pure late payment interest on settled certificates does not fit the definition of 'payment' under section 4 of CIPAA 2012 and the adjudicator exceeded jurisdiction on that portion. The adjudicated amount was reduced by RM1,610,732.87.

Why did the court find the adjudicator had exceeded her jurisdiction?

The court held that a claim for pure late-payment interest on certificates that had already been fully settled does not fall within the definition of 'payment' in section 4 of the Construction Industry Payment and Adjudication Act 2012, so that by allowing it the adjudicator acted in excess of the jurisdiction limited to the matter referred to adjudication under section 27(1).

On what grounds can an adjudication decision be set aside under section 15?

The court emphasised that an adjudication decision can be set aside only on the grounds of excess or lack of jurisdiction or a denial of natural justice under section 15, and that the court is not concerned with the merits of the decision; it therefore allowed the appeal in part to the extent of the jurisdictional excess, deducting RM1,610,732.87 with interest to be refunded.

Statutes Cited

Construction Industry Payment and Adjudication Act 2012
s 15

Cases Cited (12)

SLR (1)
[2010] 1 SLR 658
MY (11)
[1960] 1 MLJ 1 [2016] 5 CLJ 882 [2017] 4 AMR 477 [2018] 2 MLJ 22 [2019] 2 CLJ 229 [2020] 6 MLJ 224 [2020] MLJU 1272 [2020] MLJU 808 [2021] AMEJ 614 [2022] 10 CLJ 378 [2024] MLJU 70

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (b-02ca-2178-12-2024)