KPERAK IMPLEMENTATION AND COORDINATION CORPORATION v SIMFONI MAYA SDN BHD

a-02ncvcw-2264-12-2022 Court of Appeal (Mahkamah Rayuan) 4 June 2024 • A-02(NCvC)(W)-2264-12/2022 • 30 min read
44 cases cited (2 SG, 42 foreign)

Outcome

For the reasons explained, we unanimously allowed the appeal by KPerak and set aside the order of the High Court. We awarded costs here and below to10 the appellant in the amount of RM60,000, such costs to be subject to an allocatur. 14 March 2025 15 Azizul Azmi Adnan.

Quoted verbatim from the judgment of Court of Appeal (Mahkamah Rayuan) (a-02ncvcw-2264-12-2022). Read the full judgment on the official Malaysia Courts portal for the complete decision.

Catchwords

Practice Areas

Judges (3)

Counsel (9)

Parties (2)

Case Significance

Restates the rule that pre-contract surrounding circumstances may be used to construe an ambiguous contract but post-contract conduct generally cannot, and allows the appeal by setting aside a RM14.5 million damages award founded on an erroneous construction.

This Court of Appeal decision concerns the construction of a commercial contract and the limits on the use of extrinsic evidence, in an appeal against a substantial damages award for breach of an agreement. The respondent had sued the appellant, a statutory corporation, alleging that it had breached the terms of an agreement described as an indoor digital media solution agreement. After a full trial the High Court allowed the respondent's claim and ordered the appellant to pay RM14.5 million in damages. The appellant appealed. The Court of Appeal addressed the principles governing the construction of contracts where the terms are ambiguous or contradictory, in particular the extent to which evidence of surrounding circumstances may be used to interpret the contract. It held that evidence of the surrounding circumstances existing before the contract is signed may be used for the purpose of construing its terms, but that evidence of matters arising after the signing cannot be used to construe those terms — subject to recognised exceptions, such as using post-contract conduct to establish the existence of a contract, or to establish estoppel, waiver or acquiescence. Applying that framework, the Court held that neither exception applied, so that the fact that the appellant had paid RM500,000 could not be used to construe the terms of the contract; at most such a payment could show that a contract existed, but the existence of the contract was not in dispute. Concluding that the High Court had erred in its construction of the agreement, the Court of Appeal unanimously allowed the appeal and set aside the High Court's order, including the RM14.5 million award, and awarded costs here and below of RM60,000 to the appellant. The decision is a useful statement of the rule that post-contract conduct is generally inadmissible to construe the terms of a written contract.

Summary

KPerak, a Perak state-owned company, appealed after being ordered to pay RM14.5 million in damages for allegedly breaching an Indoor Digital Media Solution Agreement with Simfoni Maya Sdn Bhd for media content dissemination infrastructure. The Court of Appeal unanimously allowed KPerak's appeal, finding that the High Court erred in construing the contract terms by relying on post-contract evidence and that the RM500,000 payment could not be used to interpret the agreement's scope. The High Court order was set aside with costs of RM60,000.

What did the Court of Appeal decide about the RM14.5 million damages award?

The Court of Appeal unanimously allowed the appellant's appeal and set aside the High Court's order, including the award of RM14.5 million in damages. It held that the High Court had erred in construing the indoor digital media solution agreement, and awarded costs here and below of RM60,000 to the appellant, subject to allocatur.

To what extent could evidence outside the contract be used to construe its terms?

The Court held that evidence of the surrounding circumstances existing before the contract was signed may be used to construe its terms, but that evidence of matters arising after signing cannot be used for that purpose, save for recognised exceptions such as establishing the existence of the contract or establishing estoppel, waiver or acquiescence. Because no exception applied, the appellant's post-contract payment of RM500,000 could not be used to construe the contract's terms.

Statutes Cited

Courts of Judicature Act 1964
s 42(1)

Cases Cited (44)

SG (1)
[2013] SGCA 43
SLR (1)
[1997] 2 SLR 759
UK (10)
[1970] 1 All ER 796 [1971] 1 WLR 1381 [1974] 1 WLR 1514 [1976] 1 WLR 989 [1982] 1 QB 84 [1985] AC 191 [1995] 1 WLR 1 [1998] 1 WLR 896 [2011] UKSC 50 [2015] UKSC 36
MY (32)
[1964] 1 MLJ 239 [1987] 2 CLJ 394 [1987] 2 MLJ 466 [1988] 1 MLJ 428 [1994] 2 AMR 1631 [1994] 2 MLJ 246 [1994] 2 MLJ 754 [1994] 3 CLJ 133 [1994] 3 CLJ 172 [2004] 1 CLJ 743 [2004] 1 MLJ 401 [2004] 3 CLJ 96 [2004] 3 MLJ 38 [2005] 3 CLJ 259 [2005] 4 MLJ 101 [2007] 2 CLJ 422 [2007] 2 MLJ 610 [2010] 3 MLJ 134 [2010] 4 MLJ 157 [2010] 6 AMR 414 [2010] 8 CLJ 49 [2011] 6 MLJ 441 [2012] 3 CLJ 423 [2015] 6 MLJ 633 [2016] 1 CLJ 177 [2016] 1 MLJ 464 [2016] 4 CLJ 813 [2017] 8 CLJ 350 [2017] 9 MLJ 1 [2018] 1 CLJ 693 [2018] 1 MLJ 1 [2022] 10 CLJ 348

Judgment

Read the full judgment on the official Malaysia Courts portal.

Read on eJudgment

Source: eJudgment (a-02ncvcw-2264-12-2022)